/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q40PGB_2 The Alexander Manufacturing Comp... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

The Alexander Manufacturing Company in Rochester, Minnesota, assembles and tests electronic components used in smartphones. Consider the following data regarding component T24 (amounts are per unit):

Direct materials cost \( 81.00

Direct labor cost 21.00

Activity-based costs allocated ?

Total manufacturing product cost ?

The activities required to build the component follow:

Activity

Allocation Base

Cost Allocated to Each Unit

Start Station

Number of raw component chassis

3 X \)1.50 = \(4.50

Dip Insertion

Number of dip insertions

? X 0.50 = 14.50

Manual Insertion

Number of manual insertions

13 X 0.40 = ?

Wave solder

Number of components solders

3 X 1.50 = 4.50

Backload

Number of backload insertions

7 X ? = 2.80

Test

Number of testing hours

0.39 60.0 = ?

Defect analysis

Number of defect analysis hours

0.10 X ? = 4.00

Total activity-based costs

\) ?

Requirements

2. Why might managers favor this ABC system instead of Alexander’s older system, which allocated all manufacturing overhead costs on the basis of direct labor hours?

Short Answer

Expert verified

The activity-based costing is preferred over traditional methods due to reasonable allocation based on different activities associated with different products.

Step by step solution

01

Step-by-Step-SolutionStep 1: Activity-based costing system

Activity-based costing system is a procedure for allocating costs based on different tasks, operations, or procedures. Under activity-based costing, the overhead costs are segregated between different activities and then the different activities costs are allocated to different products or services.

02

Why activity based costing is preferred over traditional costing

Under traditional costing, the overhead costs are allocated based on a single allocation base. That allocation base may or may not be relevant to all products. So, the cost ascertained under the traditional method may be relevant for some products but may not be relevant or fair for other products.

Under activity-based costing, the overheads are allocated based on the activities associated with different products. In this way, all products are charged for the relevant activities performed for that product. So, the cost ascertained for different products under this system is relevant and fair for all products.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Refer to Exercise E19-20. For 2019, Eason’s managers have decided to use the same indirect manufacturing costs per wheel rim that they computed in 2018 using activitybasedn costing. In addition to the unit indirect manufacturing costs, the following data are expected for the company’s standard and deluxe models for 2019:

Standard Deluxe

Sales price \( 800.00 \) 940.00

Direct materials 31.00 48.00

Direct labor 45.00 52.00

Because of limited machine hour capacity, Eason can produce either2,000 standard rims or2,000 deluxe rims.

Requirements

3. Which course of action will yield more income for Eason?

Darby Corp. is considering the use of activity-based costing. The following information is provided for the production of two product lines:

Activity Cost Allocation Base

Setup \( 105,000 Number of setups

Machine maintenance 60,000 Number of machine hours

Total indirect manufacturing costs \) 165,000

Product A Product B Total

Direct labor hours 7,000 5,000 12,000

Number of setups 30 170 200

Number of machine hours 1,600 2,400 4,000

Darby plans to produce 375 units of Product A and 250 units of Product B. Compute the ABC indirect manufacturing cost per unit for each product.

Martin, Inc. manufactures bookcases and uses an activity-based costing system. Martin’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 230,000

Number of parts

\)1.50

Assembly

3,200,000

Number of assembling direct labor hours

16.00

Finishing

150,000

Number of finished units*

3.00

*Refers to the number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Martin produced two styles of bookcases in April: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

3,000

\(54,000

\)67,500

9,000

4,500

Unfinished bookcase

3,500

56,000

52,500

7,000

3,500

Requirements

1. Compute the manufacturing product cost per unit of each type of bookcase.

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

1. Compute the total estimated indirect manufacturing cost for 2018.

How is the Conversion Costs account used in JIT costing?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.