/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q8Q Question: One financial accounti... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Question: One financial accounting issue encountered when a company constructs its own plant is whether the interest cost on funds borrowed to finance construction should be capitalized and then amortized over the life of the assets constructed. What is the justification for capitalizing such interest?

Short Answer

Expert verified

Answer

Interest cost is capitalized because all cost incurred on the construction should be included in the construction cost. So, financing cost also included in the construction cost.

Step by step solution

01

Interest cost during construction

Normally companies use the three approaches to treat the interest costs. These are the:

  1. No capitalization of interest cost incurred in construction.
  2. Capitalization of all financing cost from debt or stock.
  3. Capitalization of interest cost of the debt only.
02

Reason for capitalization of interest cost

Company needs to capitalize all the cost incurred on the assets to made asset ready for use. According to this view point, company also need to capitalize the financing cost incurred in the construction of the assets. So, interest cost incurred for construction of plant assets is capitalized.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question: (Classification of Costs and Interest Capitalization) On January 1, 2017, Blair Corporation purchased for \(500,000 a tract of land (site number 101) with a building. Blair paid a real estate broker’s commission of \)36,000, legal fees of \(6,000, and title guarantee insurance of \)18,000. The closing statement indicated that the land value was \(500,000 and the building value was \)100,000. Shortly after acquisition, the building was razed at a cost of \(54,000.

Blair entered into a \)3,000,000 fixed-price contract with Slatkin Builders, Inc. on March 1, 2017, for the construction of an office building on land site number 101. The building was completed and occupied on September 30, 2018. Additional construction costs were incurred as follows:

Plans, specifications, and blueprints \(21,000

Architects’ fees for design and supervision 82,000

The building is estimated to have a 40-year life from date of completion and will be depreciated using the 150% declining balance method.

To finance construction costs, Blair borrowed \)3,000,000 on March 1, 2017. The loan is payable in 10 annual installments of \(300,000 starting on March 1, 2018, plus interest at the rate of 10%. Blair’s weighted-average amounts of accumulated building construction expenditures were as follows.

For the period March 1 to December 31, 2017 \)1,300,000

For the period January 1 to September 30, 2018 1,900,000

Instructions

  1. Prepare a schedule that discloses the individual costs making up the balance in the land account in respect of land site number 101 as of September 30, 2018.
  2. Prepare a schedule that discloses the individual costs that should be capitalized in the office building account as of September 30, 2018. Show supporting computations in good form.

Question: What interest rates should be used in determining the amount of interest to be capitalized? How should the amount of interest to be capitalized be determined?

Question: Two positions have normally been taken with respect to the recording of fixed manufacturing overhead as an element of the cost of plant assets constructed by a company for its own use: (a) It should be excluded completely. (b) It should be included at the same rate as is charged to normal operations.

What are the circumstances or rationale that support or deny the application of these methods?

Fielder Company obtained land by issuing 2,000 shares of its \(10 par value common stock. The land was recently appraised at \)85,000. The common stock is actively traded at $40 per share. Prepare the journal entry to record the acquisition of the land.

(Capitalization of Interest) On December 31, 2016, Main Inc. borrowed \(3,000,000 at 12% payable annually to finance the construction of a new building. In 2017, the company made the following expenditures related to this building: March 1, \)360,000; June 1, \(600,000; July 1, \)1,500,000; December 1, \(1,500,000. The building was completed in February 2018. Additional information is provided as follows.

1. Other debt outstanding

10-year, 13% bond, December 31, 2010, interest payable annually \)4,000,000

6-year, 10% note, dated December 31, 2014, interest payable

annually \(1,600,000

2. March 1, 2017, expenditure included land costs of \)150,000

3. Interest revenue earned in 2017 $49,000

Instructions

(a) Determine the amount of interest to be capitalized in 2017 in relation to the construction of the building.

(b) Prepare the journal entry to record the capitalization of interest and the recognition of interest expense at December 31, 2017.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.