/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q19E Question: The Watkins Company i... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Question:The Watkins Company is decentralized, and divisions are considered investment centers. Watkins specializes in sports equipment, and one division manufactures netting that is used for basketball hoops, soccer goals, and other sports equipment. The Netting Division reports the following information for a heavy-duty basketball hoop net:

Sales Price per Unit \( 18

Variable Cost per Unit 6

Contribution Margin per Unit \) 12

The Basketball Equipment Division can purchase a similar heavy-duty net from an outside vendor for $15.

Requirements

1. Determine the negotiable range for the transfer price.

2. What is the minimum transfer price the Netting Division should consider if operating at capacity? Below capacity?

3. What is the maximum transfer price the Basketball Equipment Division should consider?

Short Answer

Expert verified

Answer

Step by step solution

01

Negotiable range for the transfer price

The transaction price is the price of one unit of goods when the transaction takes place between the divisions of the same company.

Thus this transfer price would not be a fixed amount and would be set within a range.

Any division would sell its unit to outsiders at a fixed selling price. So this selling price would be the maximum transfer price.

Similarly, for any product or service, there would be a variable cost per unit. This variable cost is the margin cost below which the product or service would not be sold to anyone. Thus this variable cost per unit is the minimum transfer price.

So, in the given case the negotiable range for the transfer price is $6 - $18.

02

Transfer price at capacity and below capacity

If the division is operating at capacity, then it is producing and selling all of its capable units and would not be able to expand the facility and be able to add more employees-equipment.

Thus in this situation, the division has the choice to sell either to customers or to any other division. Because the division has the choice, the transfer price should be based on the market price which is the maximum selling price. Below this price, there would be a loss for both –the division and the company, So at capacity, the minimum transfer price for the netting division is $18.

If the division is operating below capacity it has the opportunity to sell any division at any amount equal to or above variable cost. Selling at any price above variable cost would generate more contribution for the division and would increase profit for both - the division and the company. So below capacity, the minimum transfer price for the netting division is $6.

03

Maximum transfer price to be considered

The maximum transfer price for the basketball equipment division to be considered would be the sales price per unit for the netting division. So, the maximum transfer price for the basketball division equals $18

This is the price at which the netting division sells the net to the customer. Thus basketball division would not accept any amount as a transfer price above this selling price.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Willitte Pharmaceuticals manufactures an over-the-counter allergy medication. The company sells both large commercial containers of 1,000 capsules to health care facilities and travel packs of 20 capsules to shops in airports, train stations, and hotels. The following information has been developed to determine if an activity-based costing system would be beneficial:

Activity Estimated Estimated Quantity

Indirect Cost Allocation Base of Allocation Base

Materials handling \( 95,000 Number of kilos 19,000 kilos

Packaging 200,000 Number of machine hours 5,000 hours

Quality assurance 112,500 Number of samples 1,875 samples

Total indirect costs \) 407,500

Actual production information includes the following:

Commercial Containers Travel Packs

Units produced 2,400 containers 50,000 packs

Weight in kilos 9,600 5,000

Machine hours 1,680 500

Number of samples 240 750

Requirements

4. Compare the indirect activity-based costs per unit to the indirect costs per unit from the traditional system. How have the unit costs changed? Explain why the costs changed.

Activity-based costing requires four steps. List the four steps in the order they are performed.

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

2. Prior to 2018, Eason used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

Question:High Mountain produces fleece jackets. The company uses JIT costing for its JIT production system.

High Mountain has two inventory accounts: Raw and In-Process Inventory and

Finished Goods Inventory. On April 1, 2018, the account balances were Raw and In-Process Inventory, \(10,000; Finished Goods Inventory, \)2,100.

The standard cost of a jacket is \(33, composed of \)12 direct materials plus \(21

conversion costs. Data for April’s activities follow:

Number of jackets completed 19,000

Number of jackets sold (on account for \)50 each) 18,600

Direct materials purchased (on account) \( 220,500

Conversion costs incurred \) 500,000

Requirements

1. What are the major features of a JIT production system such as that of High Mountain?

2. Prepare summary journal entries for April. Underallocated or overallocated

conversion costs are adjusted to Cost of Goods Sold monthly.

3. Use a T-account to determine the April 30, 2018, balance of Raw and In-ProcessInventory.

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.