/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q11OQ Old Pueblo Engineering Contracto... [FREE SOLUTION] | 91影视

91影视

Old Pueblo Engineering Contractors create six-month 鈥渞olling鈥 schedules, which are recomputed monthly. For competitive reasons (it would need to divulge proprietary design criteria, methods, and so on), Old Pueblo does not subcontract. Therefore, its only options to meet customer requirements are (1) work on regular time; (2) work overtime, which is limited to 30 percent of the regular time; (3) do customers鈥 work early, which would cost an additional \(5 per hour per month; and (4) perform customers鈥 work late, which would cost an additional \)10 per hour per month penalty, as provided by their contract. Old Pueblo has 25 engineers on its staff at an hourly rate of \(30. The overtime rate is \)45. Customers鈥 hourly requirements for the six months from January to June are

January

February

March

April

May

June

5,000

4,000

6,000

6,000

5,000

4,000

Develop an aggregate plan using a spreadsheet. Assume 20 working days in each month.

Short Answer

Expert verified

It is very necessary for the company to plan its production schedule so that optimal use of available sources can be done. Following the following steps will lead the company to maximize its output production and therefore increase its revenue.

Step by step solution

01

Given data

Total staff = 25

Working days per month = 20

Straight time rate = $30

Overtime rate = $45

Carrying cost = $5 per hour per month

Overtime = 30% of straight time

Backorder cost = $10 per hour per month

02

Calculate the available hours per month

Let鈥檚 suppose the working hours per day is 8 hours

Working hours per month per worker = working days x working hours

= 20 x 8

= 160 hours

Straight time hours available per month = 25 x 160 hours

= 4000 hours

Overtime hours available = 0.30 x 4000

= 1200 hours

03

Prediction of the calculated hours

From the calculations, it is clear that the estimated demandcannot be met by working in regular hoursexcept for the month of February and June. Thus, the company needs to workextra hoursto full fill the demand.

To full fill such demand there can be two possible ways for the company and those are:

  1. Regular production and meeting the remaining demand by doing overtime in early time.

2. One can also full fill the demand by working in the delayed time.

We need to calculate the total cost in both conditions.

Straight time cost = Straight time hours x $30

Overtime cost = Overtime hours used x 45

Cost of doing the work late = Delayed work hours x 10

Cost of working early = Early worked hours x 55

04

Work on a regular time in early production

The costof the first alternative is $1,065,000.

05

Work on regular time in delayed production

The cost of alternative 2 is $934,000.

Alternate 2 should be followed by the company

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91影视!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Visit the vendors鈥 websites to read up on both SAP and Microsoft Dynamics ERP systems. Provide a list of four ways in which the two differ in their approach to implementing ERP

CU, Incorporated, (CUI) produces copper contacts that it uses in switches and relays. CUI needs to determine the order quantity, Q, to meet the annual demand at the lowest cost. The price of copper depends on the quantity ordered. Here are price-break and other data for the problem:

Price of copper

\(0.82 per pound up to 2,499 pounds

\)0.81 per pound for orders between 2,500 and 5,000 pounds \(0.80 per pound for orders greater than 5,000 pounds

Annual demand

50,000 pounds per year

Holding cost

20 percent per unit per year of the price of the copper

Ordering cost

\)30

Which quantity should be ordered?

Charlie鈥檚 Pizza orders all of its pepperoni, olives, anchovies, and mozzarella cheese to be shipped directly from Italy. An American distributor stops by every four weeks to take orders. Because the orders are shipped directly from Italy, they take three weeks to arrive. Charlie鈥檚 Pizza uses an average of 150 pounds of pepperoni each week, with a standard deviation of 30 pounds. Charlie鈥檚 prides itself on offering only the best quality ingredients and a high level of service, so it wants to ensure a 98 percent probability of not stocking out on pepperoni. Assume that the sales representative just walked in the door and there are currently 500 pounds of pepperoni in the walk-in cooler. How many pounds of pepperoni would you order?

Plan production for the next year. The demand forecast is spring, 20,000; summer, 10,000; fall, 15,000; winter, 18,000. At the beginning of spring, you have 70 workers and 1,000 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of summer and the number hired at the end of summer should result in planned production levels for summer and fall that equal the demand forecasts for summer and fall, respectively. If demand exceeds supply, use overtime in spring only, which means that backorders could occur in winter. You are given these costs: hiring, \(100 per new worker; layoff, \)200 per worker laid off; holding, \(20 per unit-quarter; backorder cost, \)8 per unit; straight-time labor, \(10 per hour; over time, \)15 per hour. Productivity is 0.5 units per worker hour, eight hours per day, and 50 days per quarter. Find the total cost.

Sales data for two years are as follows. Data are aggregated with two months of sales in each 鈥減eriod.鈥

Months

Sales

闯补苍耻补谤测鈥揊别产谤耻补谤测

109

惭补谤肠丑鈥揂辫谤颈濒

104

惭补测鈥揓耻苍别

150

闯耻濒测鈥揂耻驳耻蝉迟

170

厂别辫迟别尘产别谤鈥揙肠迟辞产别谤

120

狈辞惫别尘产别谤鈥揇别肠别尘产别谤

100

Months

Sales

闯补苍耻补谤测鈥揊别产谤耻补谤测

115

惭补谤肠丑鈥揂辫谤颈濒

112

惭补测鈥揓耻苍别

159

闯耻濒测鈥揂耻驳耻蝉迟

182

厂别辫迟别尘产别谤鈥揙肠迟辞产别谤

126

狈辞惫别尘产别谤鈥揇别肠别尘产别谤

106

a. Plot the data.

b. Fit a simple linear regression model to the sales data.

c. In addition to the regression model, determine multiplicative seasonal index factors. A full cycle is assumed to be a full year.

d. Using the results from parts (b) and (c), prepare a forecast for the next year.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.