/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q42PGB_1 Rennie Plant Service completed a... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Brenton job?

Short Answer

Expert verified

Total cost of Brenton job: $1,690

Step by step solution

01

Step-by-Step-SolutionStep 1: Total overhead cost

Designcost=No.ofdesigns×Predeterminedoverheadallocationrate=1×$290=$290

role="math" localid="1653289750404" Plantingcost=No.ofplants×Predeterminedoverheadallocationrate=30×$20=$600

role="math" localid="1653289898905" Totaloverheadcost=Designcost+Plantingcost=$290+$600=$890

02

Total cost of Brenton job

Totalcost=Directlaborcost+Totaloverheadcost=$800+$890=$1,690

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

The following information is provided for Orbit Antenna Corp., which manufactures two products: Lo-Gain antennas and Hi-Gain antennas for use in remote areas.

Activity Cost Allocation Base

Setup \( 58,000 Number of setups

Machine maintenance 30,000 Number of machine hours

Total indirect manufacturing costs \) 88,000

Lo-Gain Hi-Gain Total

Direct labor hours 1,200 3,800 5,000

Number of setups 40 40 80

Number of machine hours 3,000 2,000 5,000

Orbit Antenna plans to produce 125 Lo-Gain antennas and 225 Hi-Gain antennas.

Requirements

2. Compute the ABC indirect manufacturing cost per unit for each product.

Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscar’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

3. Which product costs are reported in the external financial statements? Which costs are used for management decision-making? Explain the difference.

Refer to Exercise E19-20. For 2019, Eason’s managers have decided to use the same indirect manufacturing costs per wheel rim that they computed in 2018 using activity based n costing. In addition to the unit indirect manufacturing costs, the following data are expected for the company’s standard and deluxe models for 2019:

Standard Deluxe

Sales price \( 800.00 \) 940.00

Direct materials 31.00 48.00

Direct labor 45.00 52.00

Because of limited machine hour capacity, Eason can produce either2,000 standard rims or2,000 deluxe rims.

Requirements

2. If the managers rely on the single plantwide overhead allocation rate cost data, which model will they produce?

Refer to Exercises E19-20 and E19-21. Controller Michael Bender is surprised by the increase in cost of the deluxe model under ABC. Market research shows that for the deluxe rim to provide a reasonable profit, Eason will have to meet a target manufacturing cost of \(625.00 per rim. A value engineering study by Eason’s employees suggests that modifications to the finishing process could cut finishing cost from \)90.00 to \(60.00 per hour and reduce the finishing direct labor hours per deluxe rim from 5.50 hours to 5.0 hours. Direct materials would remain unchanged at \)48.00 per rim, as would direct labor at $52.00 per rim. The materials handling, machine setup, and insertion of parts activity costs also would remain the same.

Would implementing the value engineering recommendation enable Eason to achieve its target cost for the deluxe rim?

Question:Refer to Exercises E19-24 and E19-25. Suppose Western’s direct labor rate was $280 per hour. The Halbert engagement used the following resources last month:

Allocation Base Halbert

Direct labor hours 170

Pages 310

Applications used 80

Requirements

1. Compute the cost assigned to the Halbert engagement, using the ABC system.

2. Compute the operating income or loss from the Halbert engagement, using theABC system.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.