/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} 19-22E Refer to Exercises E19-20 and E1... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Refer to Exercises E19-20 and E19-21. Controller Michael Bender is surprised by the increase in cost of the deluxe model under ABC. Market research shows that for the deluxe rim to provide a reasonable profit, Eason will have to meet a target manufacturing cost of \(625.00 per rim. A value engineering study by Eason’s employees suggests that modifications to the finishing process could cut finishing cost from \)90.00 to \(60.00 per hour and reduce the finishing direct labor hours per deluxe rim from 5.50 hours to 5.0 hours. Direct materials would remain unchanged at \)48.00 per rim, as would direct labor at $52.00 per rim. The materials handling, machine setup, and insertion of parts activity costs also would remain the same.

Would implementing the value engineering recommendation enable Eason to achieve its target cost for the deluxe rim?

Short Answer

Expert verified

The value engineering program can be implemented as the new cost is lower than the target cost.

New cost: $524.4

Step by step solution

01

New finishing cost as per value engineering program

Finishingcost=Revisedfinishingrate×RevisedFinishingdirectlaborhour=$60×5=$300

02

Computation of total indirect cost

Perrimmaterialhandlingcost=Predeterminedoverheadallocationrate×Numberofpartsperunit=$4×7=$28PerrimMachinesetupcost=Predeterminedoverheadallocationrate×Numberofsetupsper500units500=$400×18500=$14.4Perriminsertionofpartscost=Predeterminedoverheadallocationrate×Numberofpartsperunit=$26×7=$182Perrimindirectforstandardmodel=Materialhandlingcost+Machinesetupcost+Insertionofpartscost+Finishingcost=$28+$14.4+$182+$300=$524.4

The New per rim cost for the deluxe rim amounts to $524.4. This cost is lower than the target cost. So it is recommended to implement the value engineering program.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Harcourt Pharmaceuticals manufactures an over-the-counter allergy medication. The company sells both large commercial containers of 1,000 capsules to health care facilities and travel packs of 20 capsules to shops in airports, train stations, and hotels. The following information has been developed to determine if an activity-based costing system would be beneficial:

Activity Estimated Estimated Quantity

Indirect Cost Allocation Base of Allocation Base

Materials handling \( 96,000 Number of kilos 24,000 kilos

Packaging 210,000 Number of machine hours 3,000 hours

Quality assurance 114,000 Number of samples 1,900 samples

Total indirect costs \) 420,000

Other production information includes the following:

Commercial Containers Travel Packs

Units produced 2,800 containers 51,000 packs

Weight in kilos 9,800 5,100

Machine hours 1,960 510

Number of samples 560 765

Requirements

2. Compute the predetermined overhead allocation rate for each activity.

Question:Gateway produces electronic calculators. Suppose Gateway’s standard cost per calculator is \(25 for direct materials and \)68 for conversion costs. The following data applyto August activities:

Direct materials purchased (on account) \( 8,300

Conversion costs incurred 20,500

Number of calculators produced 300 calculators

Number of calculators sold (on account, at \)105 each) 295 calculators

Requirements

1. Prepare summary journal entries for August using JIT costing, including the entryto adjust the Conversion Costs account.

2. The beginning balance of Finished Goods Inventory was $1,300. Use a T-accountto find the ending balance of Finished Goods Inventory.

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

2. Prior to 2018, Eason used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

Haworth Company is a management consulting firm. The company expects to incur \(167,500 of indirect costs this year. Indirect costs are allocated based on the following activities:

Activity

Estimated cost

Allocation Base

Estimated quantity of allocation base

Predetermined

Overhead allocation rate

Site visits

\) 45,000

Number of visits

900 visits

\( 50 per visit

Documentation Preparation

122,500

Number of pages

3,500 Pages

\) 35 per page

Total Indirect costs

\( 167,500

Haworth bills clients at 120% of the direct labor costs. The company has estimated direct labor costs at \)240 per hour. Last month, Haworth completed a consulting job for Client 76 and used the following resources:

Allocation Base Client 76

Direct labor hours 60

Visits 5

Pages 50

Determine the total cost of the consulting job and the operating income earned.

Define value engineering. How is it used to control costs?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.