/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q. 19-6SE_1 The following information is pro... [FREE SOLUTION] | 91影视

91影视

The following information is provided for Orbit Antenna Corp., which manufactures two products: Lo-Gain antennas and Hi-Gain antennas for use in remote areas.

Activity Cost Allocation Base

Setup \( 58,000 Number of setups

Machine maintenance 30,000 Number of machine hours

Total indirect manufacturing costs \) 88,000

Lo-Gain Hi-Gain Total

Direct labor hours 1,200 3,800 5,000

Number of setups 40 40 80

Number of machine hours 3,000 2,000 5,000

Orbit Antenna plans to produce 125 Lo-Gain antennas and 225 Hi-Gain antennas.

Requirements

1. Compute the indirect manufacturing cost per unit using direct labor hours for the single plantwide predetermined overhead allocation rate.

Short Answer

Expert verified

Per unit indirect cost

For Lo-Gain:$168.96

For Hi-Gain: $297.24

Step by step solution

01

Computation of predetermined overhead rate under single plantwide allocation

predeterminedoverheadrate=totalindirectmanufacturingcosttotaldirectlaborhours=$88,0005,000=$17.6

02

Computation of per unit indirect cost for Lo-Gain

perunitindirectcost=predeterminedoverheadrateno.ofdirectlaborhourrequiredno.ofunitsproduced=$17.61,200125=$21,120125=$168.96

03

Computation of per unit indirect cost for Hi-Gain

perunitindirectcost=predeterminedoverheadrateno.ofdirectlaborhourrequiredno.ofunitsproduced=$17.63,800225=$66,880225=$297.24

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91影视!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Consider the following characteristics of either a JIT production system or a traditional production system. Indicate whether each is characteristic of a JIT production system or a traditional production system.

a. Products are produced in large batches.

b. Large stocks of finished goods protect against lost sales if customer demand ishigher than expected.

c. Suppliers make frequent deliveries of small quantities of raw materials.

d. Employees do a variety of jobs, including maintenance and setups as well as operating machines.

e. Machines are grouped into self-contained production cells or production lines.

f. Machines are grouped according to function. For example, all cutting machines are located in one area.

g. The final operation in the production sequence 鈥減ulls鈥 parts from the preceding operation.

h. Each employee is responsible for inspecting his or her own work.

i. Management works with suppliers to ensure defect-free raw materials.

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

Question:The Watkins Company is decentralized, and divisions are considered investment centers. Watkins specializes in sports equipment, and one division manufactures netting that is used for basketball hoops, soccer goals, and other sports equipment. The Netting Division reports the following information for a heavy-duty basketball hoop net:

Sales Price per Unit \( 18

Variable Cost per Unit 6

Contribution Margin per Unit \) 12

The Basketball Equipment Division can purchase a similar heavy-duty net from an outside vendor for $15.

Requirements

1. Determine the negotiable range for the transfer price.

2. What is the minimum transfer price the Netting Division should consider if operating at capacity? Below capacity?

3. What is the maximum transfer price the Basketball Equipment Division should consider?

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

2. Prior to 2018, Eason used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

Stegall, Inc. manufactures motor scooters. For each of the following examples of quality costs, indicate which of the following quality cost categories each example represents: prevention costs, appraisal costs, internal failure costs, or external failure costs.

1. Preventive maintenance on machinery

2. Direct materials, direct labor, and manufacturing overhead incurred to rework a defective scooter that is detected in-house through inspection

3. Lost profits from lost sales if the company鈥檚 reputation is hurt because customers previously purchased a poor-quality scooter

4. Cost of inspecting raw materials, such as chassis and wheels

5. Working with suppliers to achieve on-time delivery of defect-free raw materials

6. Cost of warranty repairs on a scooter that malfunctions at a customer鈥檚 location

7. Costs of testing durability of vinyl

8. Cost to reinspect reworked scooters

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.