/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q6OQ. Which of the four costs relevant... [FREE SOLUTION] | 91影视

91影视

Which of the four costs relevant to aggregate production planning is the most difficult to accurately measure?

Short Answer

Expert verified

Aggregate planning is a technique for fostering a general assembling plan that guarantees continuous creation at an office.A few instances of aggregate planning are recruiting transitory specialists, laying off representatives for a particular period, or broadly educating. This functions as a compelling benchmark to quantify asset use and implementation.

Four costs pulled in with the aggregate production plan incorporate-

  1. Basic production costs
  2. Costs associated with changes in the production rate
  3. Inventory holding costs
  4. Backordering costs

Step by step solution

01

The four major costs are

The four major costs are as follows

  1. Production cost: These are fixed, and variable costs brought about in delivering a given item type in a given period. Included are immediate and roundabout work expenses and customary as well as extra time remuneration.
  2. Setup cost and equipment installment cost:Normal expenses in this classification are those associated with employing, preparing, and laying off staff. Employing impermanent assistance is an approach to keeping away from these expenses
  3. Inventory holding cost: A significant part is the expense of capital restricted in stock. Different parts are capacity, protection, assessments, waste, and outdated nature.
  4. Backordering costs: Backordering costs incorporate costs achieved by a business when it can't speedily deal with a solicitation and ensures the client that it will be done with a later transport date.
02

Conclusion

Backordering costs,typically square measure improbably difficult to visualize and solidify prices of serving to the deficiency of shopper benevolence, and loss of plans earnings going on considering deferred buys.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91影视!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question: In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.

Week Number

Item J012345
Gross Requirement

75
5070
On-hand40




Net Requirement





Planned order receipt





Planned order release





Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gearboxes and input shafts. These costs are as follows:

Part

Cost

Gear Box

Step up = \(90 / order

Inventory carrying cost = \) 2/unit/week

Input Shaft

Set up = \(45/ order

Inventory carrying cost = \) 1/unit/week

Old Pueblo Engineering Contractors create six-month 鈥渞olling鈥 schedules, which are recomputed monthly. For competitive reasons (it would need to divulge proprietary design criteria, methods, and so on), Old Pueblo does not subcontract. Therefore, its only options to meet customer requirements are (1) work on regular time; (2) work overtime, which is limited to 30 percent of the regular time; (3) do customers鈥 work early, which would cost an additional \(5 per hour per month; and (4) perform customers鈥 work late, which would cost an additional \)10 per hour per month penalty, as provided by their contract. Old Pueblo has 25 engineers on its staff at an hourly rate of \(30. The overtime rate is \)45. Customers鈥 hourly requirements for the six months from January to June are

January

February

March

April

May

June

5,000

4,000

6,000

6,000

5,000

4,000

Develop an aggregate plan using a spreadsheet. Assume 20 working days in each month.

The widespread scientific application of yield management began within what industry?

Gentle Ben鈥檚 Bar and Restaurant uses 5,000-quart bottles of imported wine each year. The effervescent wine costs \(3 per bottle and is served only in whole bottles because it loses its bubbles quickly. Ben FIgures that it costs \)10 each time an order is placed, and holding costs are 20 percent of the purchase price. It takes three weeks for an order to arrive. Weekly demand is 100 bottles (closed two weeks per year) with a standard deviation of 30 bottles. Ben would like to use an inventory system that minimizes inventory cost and will provide a 95 percent service probability.

a. What is the economic quantity for Ben to order?

b. At what inventory level should he place an order?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.