/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q5BE. Ismail Construction enters into ... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Ismail Construction enters into a contract to design and build a hospital. Ismail is responsible for the overall management of the project and identifies various goods and services to be provided, including engineering, site clearance, foundation, procurement, construction of the structure, piping and wiring, installation of equipment, and finishing. Does Ismail have a single performance obligation to the customer in this revenue arrangement? Explain.

Short Answer

Expert verified

Ismail accounts for the bundle of products and services as a single performance obligation since the commodities or services are intricately interrelated.

Step by step solution

01

Meanings of Revenue Arrangement

Revenue elements are contained in Revenue Arrangements (performance obligations). Revenue Rule, the start of revenue plan and end dates, and revenue allotted amount are all distinct properties of elements.

02

Performance obligations in this revenue arrangement

Because the commodities or services in the bundle are intimately interconnected, Ismail accounts for the bundle of goods and services as a single performance obligation. Ismail also offers a valuable service by combining the commodities or services into a single commodity (the hospital) the consumer has contracted. In addition, to satisfy the contract, the goods or services are considerably changed and personalized. In another way, the company's goal is to convey a bundled item. Revenue for the performance obligation would be recognized over time by adopting an acceptable measure of progress toward fulfillment.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Wood-Mode Company is involved in the design, manufacture, and installation of various types of wood products for large construction projects. Wood-Mode recently completed a large contract for Stadium Inc., which consisted of building 35 different types of concession counters for a new soccer arena under construction. The terms of the contract are that upon completion of the counters, Stadium would pay \(2,000,000. Unfortunately, due to the depressed economy, the completion of the new soccer arena is now delayed. Stadium has therefore asked Wood-Mode to hold the counters for 2 months at its manufacturing plant until the arena is completed. Stadium acknowledges in writing that it ordered the counters and that they now have ownership. The time that Wood-Mode Company must hold the counters is totally dependent on when the arena is completed. Because Wood-Mode has not received additional progress payments for the counters due to the delay, Stadium has provided a deposit of \)300,000.

Instructions

(a) Explain this type of revenue recognition transaction.

(b) What factors should be considered in determining when to recognize revenue in this transaction?

(c) Prepare the journal entry(ies) that Wood-Mode should make, assuming it signed a valid sales contract to sell the counters and received at the time the $300,000 deposit.

Question: P18-11 (LO5,6,7) EXCEL (Long-Term Contract with an Overall Loss) On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of \(1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019.

At 12/31/17

At 12/31/18

At 12/31/19

Contract cost incurred to date

\)300,000

\(1,200,000

\)2,100,000

Estimated cost to complete contract

1,200,000

800,000

0

Billings to Gumbel

300,000

1,100,000

1,850,000

Instructions

Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)

Refer to the revenue arrangement in E18-10. Repeat the requirements, assuming (a) Geraths estimates the standalone selling price of the installation based on an estimated cost of $400 plus a margin of 20% on cost, and (b) given uncertainty of finding skilled labor, Geraths is unable to develop a reliable estimate for the standalone selling price of the installation. (Round amounts to nearest dollar.)

Zagat Inc. enters into an agreement on March 1, 2017, to sell Werner Metal Company aluminum ingots. As part of the agreement, Zagat also agrees to repurchase the ingots on May 1, 2017, at the original sales price of $200,000 plus 2%.

Instructions

(a) Prepare Zagat’s journal entry necessary on March 1, 2017.

(b) Prepare Zagat’s journal entry for the repurchase of the ingots on May 1, 2017.

(Allocate Transaction Price) Crankshaft Company manufactures equipment. Crankshaft’s products range from simple automated machinery to complex systems containing numerous components. Unit selling prices range from \(200,000 to \)1,500,000 and are quoted inclusive of installation. The installation process does not involve changes to the features of the equipment and does not require proprietary information about the equipment in order for the installed equipment to perform to specifications. Crankshaft has the following arrangement with Winkerbean Inc.

• Winkerbean purchases equipment from Crankshaft for a price of \(1,000,000 and contracts with Crankshaft to install the equipment. Crankshaft charges the same price for the equipment irrespective of whether it does the installation or not. Using market data, Crankshaft determines installation service is estimated to have a standalone selling price of \)50,000. The cost of the equipment is \(600,000.

• Winkerbean is obligated to pay Crankshaft the \)1,000,000 upon the delivery and installation of the equipment.

Crankshaft delivers the equipment on June 1, 2017, and completes the installation of the equipment on September 30, 2017. The equipment has a useful life of 10 years. Assume that the equipment and the installation are two distinct performance obligations which should be accounted for separately.

Instructions

(a) How should the transaction price of $1,000,000 be allocated among the service obligations?

(b) Prepare the journal entries for Crankshaft for this revenue arrangement on June 1, 2017 and September 30, 2017, assuming Crankshaft receives payment when installation is completed.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.