/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q.18-11_1 Question: P18-11 (LO5,6,7) EXCEL... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Question: P18-11 (LO5,6,7) EXCEL (Long-Term Contract with an Overall Loss) On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of \(1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019.

At 12/31/17

At 12/31/18

At 12/31/19

Contract cost incurred to date

\)300,000

\(1,200,000

\)2,100,000

Estimated cost to complete contract

1,200,000

800,000

0

Billings to Gumbel

300,000

1,100,000

1,850,000

Instructions

Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)

Short Answer

Expert verified

Answer

Profit

2017:$80,000

2018:$20,000

2019:($300,000)

Step by step solution

01

Definition of Gross Profit

A financial metric determining the profitability of the business entity by adjusting the direct costs with the revenue generated is known as gross profit.

02

Gross profit under the percentage of completion method

Particular

2017

2018

2019

Revenue recognized

$380,000

$1,140,000

$1,900,000

Less: Cost to date

(300,000)

(1,200,000)

(2,100,000)

Gross profit

$80,000

($60,000)

($200,000)

Less: Gross profit recognized in the previous year

0

$80,000

($100,000)

Profit

$80,000

$20,000

$300,000

Working note:

Particular

2017

2018

2019

Cost to date (A)

$300,000

$1,200,000

$2,100,000

Add: Estimated cost to complete contract

$1,200,000

$800,000

$0

Estimated total cost (C)

$1,500,000

$2,000,000

$2,100,000

Percentage of completion

AC×100

20%

60%

100%

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Tablet Tailors sells tablet PCs combined with Internet service, which permits the tablet to connect to the Internet anywhere and set up a Wi-Fi hot spot. It offers two bundles with the following terms.

1. Tablet Bundle A sells a tablet with 3 years of Internet service. The price for the tablet and a 3-year Internet connection service contract is \(500. The standalone selling price of the tablet is \)250 (the cost to Tablet Tailors is \(175). Tablet Tailors sells the Internet access service independently for an upfront payment of \)300. On January 2, 2017, Tablet Tailors signed 100 contracts, receiving a total of \(50,000 in cash.

2. Tablet Bundle B includes the tablet and Internet service plus a service plan for the tablet PC (for any repairs or upgrades to the tablet or the Internet connections) during the 3-year contract period. That product bundle sells for \)600. Tablet Tailors provides the 3-year tablet service plan as a separate product with a standalone selling price of \(150. Tablet Tailors signed 200 contracts for Tablet Bundle B on July 1, 2017, receiving a total of \)120,000 in cash.

Instructions

(b) Prepare any journal entries to record the revenue arrangement for Tablet Bundle B on July 1, 2017, and December 31, 2017.

In September 2017, Gaertner Corp. commits to selling 150 of its iPhone-compatible docking stations to Better Buy Co. for \(15,000 (\)100 per product). The stations are delivered to Better Buy over the next 6 months. After 90 stations are delivered, the contract is modified and Gaertner promises to deliver an additional 45 products for an additional \(4,275 (\)95 per station). All sales are cash on delivery.

Instructions

(a) Prepare the journal entry for Gaertner for the sale of the first 90 stations. The cost of each station is $54.

(b) Prepare the journal entry for the sale of 10 more stations after the contract modification, assuming that the price for the additional stations reflects the standalone selling price at the time of the contract modification. In addition, the additional stations are distinct from the original products as Gaertner regularly sells the products separately.

(c) Prepare the journal entry for the sale of 10 more stations (as in (b)), assuming that the pricing for the additional products does not reflect the standalone selling price of the additional products and the prospective method is used.

On March 1, 2017, Parnevik Company sold goods to Goosen Inc. for \(660,000 in exchange for a 5-year, zerointerest-bearing note in the face amount of \)1,062,937 (an inputed rate of 10%). The goods have an inventory cost on Parnevik’s books of $400,000. Prepare the journal entries for Parnevik on (a) March 1, 2017, and (b) December 31, 2017.

Question: (Allocate Transaction Price) Refer to the revenue arrangement in E18-13.

Instructions

Repeat requirements (a) and (b) assuming Crankshaft does not have market data with which to determine the standalone selling price of the installation services. As a result, an expected cost plus margin approach is used. The cost of installation is $36,000; Crankshaft prices these services with a 25% margin relative to cost.

(Allocate Transaction Price, Modification of Contract) Refer to the Tablet Bundle A revenue arrangement in P18-1. In response to competitive pressure for Internet access for Tablet Bundle A, after 2 years of the 3-year contract, Tablet Tailors offers a modified contract and extension incentive. The extended contract services are similar to those provided in the first 2 years of the contract. Signing the extension and paying $90 (which equals the standalone selling of the revised Internet service package) extends access for 2 more years of Internet connection. Forty Tablet Bundle A customers sign up for this offer.

Instructions

(a) Prepare the journal entries when the contract is signed on January 2, 2019, for the 40 extended contracts. Assume the modification does not result in a separate performance obligation.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.