Chapter 4: Problem 42
16 persons can reap \(\frac{1}{5}\) th field in 6 days. How many persons (with same efficiency) are required to reap rest of the field in 8 days? (a) 27 (b) 54 (c) 48 (d) 64
Short Answer
Expert verified
Answer: 48 persons.
Step by step solution
01
Calculate the person-days required to reap the entire field
Let x be the number of person-days to reap the entire field. Since 16 persons can reap \(\frac{1}{5}\)th of the field in 6 days, we can represent this as:
$$\frac{1}{5}x = 16 \times 6$$
02
Solve for x
Now we will solve for x:
$$x = 5 (16 \times 6) = 5(96) = 480$$
So the entire field requires 480 person-days to be reaped.
03
Subtract the person-days required for the first \(\frac{1}{5}\)th of field
As calculated above, \(\frac{1}{5}x = 16 \times 6 = 96\) person-days were required for the first \(\frac{1}{5}\)th of the field.
We need to find the person-days required for the remaining \(\frac{4}{5}\)th of the field:
$$480 - 96 = 384$$
So, 384 person-days are required for the remaining \(\frac{4}{5}\)th of the field.
04
Calculate the number of persons
Since we have to reap the remaining field in 8 days, we need to find out the number of persons required for these 384 person-days. Let's denote the required number of persons as y:
$$y \times 8 = 384$$
05
Solve for y
Now we will solve for y:
$$y = \frac{384}{8} = 48$$
So, 48 persons are required to reap the remaining \(\frac{4}{5}\)th of the field in 8 days. The correct answer is (c) 48.
Unlock Step-by-Step Solutions & Ace Your Exams!
-
Full Textbook Solutions
Get detailed explanations and key concepts
-
Unlimited Al creation
Al flashcards, explanations, exams and more...
-
Ads-free access
To over 500 millions flashcards
-
Money-back guarantee
We refund you if you fail your exam.
Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!
Key Concepts
These are the key concepts you need to understand to accurately answer the question.
Person-Days Calculation
In work and time problems, the concept of person-days is crucial. Person-days calculate the total amount of work done based on the number of people working and the number of days they work. Think of it as a measure of the total effort needed to complete a task.
To calculate person-days, you multiply the number of persons by the number of days they work. For instance, if it takes 16 people 6 days to complete \(\frac{1}{5}\) of a task, you would calculate the person-days as follows:
To calculate person-days, you multiply the number of persons by the number of days they work. For instance, if it takes 16 people 6 days to complete \(\frac{1}{5}\) of a task, you would calculate the person-days as follows:
- Number of persons = 16
- Number of days = 6
- Person-days for \(\frac{1}{5}\) of the task = 16 \times 6 = 96 person-days
Fraction of Work
In these problems, the work is often divided into fractions to facilitate calculation. Fractions of work denote portions of the task completed, usually shown as a part of the whole task. For example, if a task is divided into 5 parts, each representing \(\frac{1}{5}\) of the total job, completing one part is depicted as having completed \(\frac{1}{5}\) of the work.
Applying this to our problem:
Applying this to our problem:
- The initial work done by 16 persons in 6 days is \(\frac{1}{5}\) of the entire task.
- This allows us to gauge how much effort is theoretically needed to complete the remaining \(\frac{4}{5}\) of the task.
Efficiency in Work
Efficiency refers to the rate at which work is done. In this context, it implies how effectively the labor force completes a given portion of the task in a certain timeframe. If all the workers have the same rate of working, their collective efficiency can be considered uniform.
For our exercise:
For our exercise:
- Given that 16 people can complete \(\frac{1}{5}\) of the job in 6 days encapsulates their efficiency.
- The efficiency remains constant whether calculated over \(\frac{1}{5}\) or \(\frac{4}{5}\) of the work.
Algebraic Equations
Algebraic equations serve a powerful role in solving work and time problems. They offer an organized method for expressing unknowns and knowns to find solutions related to manpower and timeframe.
In the given problem:
In the given problem:
- Equations were set up to find the total person-days necessary to finish the complete work.
- By expressing unknown outputs like total person-days (\(x\)) and persons required (\(y\)), calculations became manageable.
- The equations \(\frac{1}{5}x = 16 \times 6\) and \(y \times 8 = 384\) were central to determining \(x\) and \(y\).