/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Problem 68 A company is producing a new pro... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

A company is producing a new product, and the time required to produce each unit decreases as workers gain experience. It is determined that $$T(x)=2+0.3\left(\frac{1}{x}\right)$$ where \(T(x)\) is the time, in hours, required to produce the \(x\) th unit. Use this information. Find the total time required for a worker to produce units 1 through 20 ; units 20 through 40 .

Short Answer

Expert verified
The total time for units 1-20 is approximately 42.03 hours, and for units 20-40, it's approximately 39.92 hours.

Step by step solution

01

Understanding the Problem

The problem gives a function \(T(x) = 2 + 0.3\left(\frac{1}{x}\right)\) that represents the time in hours required to produce the \(x\)th unit. We need to find the total time to produce units 1 through 20 and units 20 through 40.
02

Calculating Time for Units 1 through 20

The total time for units 1 through 20 is the sum \(T(1) + T(2) + \ldots + T(20)\). We calculate each \(T(x)\) and add them together.
03

Calculating Time for Units 20 through 40

The total time for units 20 through 40 is the sum \(T(21) + T(22) + \ldots + T(40)\). Like before, calculate each \(T(x)\) and sum them.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

Key Concepts

These are the key concepts you need to understand to accurately answer the question.

Learning Curve
The learning curve is a concept that describes how efficient workers become as they gain more experience and skills while performing a repetitive task. When a new task is introduced, workers often require more time to complete each unit. However, as they repeat the task, they learn better techniques and become more familiar, ultimately reducing the time needed per unit.

In the context of the given exercise, the learning curve is represented by the function \[ T(x) = 2 + 0.3\left(\frac{1}{x}\right). \]
  • Here, \( T(x) \) indicates the time required to produce the \( x \)th unit.
  • The formula shows that as \( x \) increases, the term \( 0.3\left(\frac{1}{x}\right) \), which depicts the learning aspect, decreases.
This reflects the idea that initially, the time decrease is more significant but reduces gradually as the worker gains experience.
Production Function
In economics and manufacturing, a production function describes the relationship between input resources and the resulting output. Essentially, it provides a mathematical way of describing how resources are transformed into products.

The function given in the problem, \[ T(x) = 2 + 0.3\left(\frac{1}{x}\right), \] demonstrates elements of a production function because it links the task of producing a unit (output) to the experience level, represented by the number \( x \), which can be considered an input.
  • The constant term 2 represents a base time required for the production, regardless of experience levels.
  • The term \( 0.3\left(\frac{1}{x}\right) \) indicates how the experience (input) impacts production time (output).
Such a function aids in strategically understanding and optimizing production processes by quantitatively capturing efficiency improvements with experience.
Summation in Calculus
Summation is a mathematical operation that involves adding a sequence of numbers, usually its function values across an interval. In calculus, it often deals with summing discrete values, as seen in the provided exercise.

To find the total time for producing a certain number of units, we sum the values of the function for each individual unit. The total time to produce units from 1 to 20 and from 20 to 40 is calculated by summing up:
  • \( T(1) + T(2) + \ldots + T(20) \) for the first interval
  • \( T(21) + T(22) + \ldots + T(40) \) for the second interval.
This approach of applying summation gives a precise total for the required production time across defined units. Moreover, it illustrates how calculus techniques can help simplify and solve real-world problems that involve accumulating effects, such as total working time or cumulative production cost over time.

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Calculate total cost (disregarding any fixed costs) or total profit. Total profit from marginal profit. A concert promoter sells \(x\) tickets and has a marginal-profit function given by $$P^{\prime}(x)=2 x-150$$ where \(P^{\prime}(x)\) is in dollars per ticket. This means that the rate of change of total profit with respect to the number of tickets sold, \(x\), is \(P^{\prime}(x)\). Find the total profit from the sale of the first 300 tickets.

Find each integral. $$ \int x^{7} d x $$

Occasionally, integration by parts yields an integral of the form \(\int u d v\) that is identical to the original integral. In some cases, we can then solve for \(\int u d v\) algebraically. For example, to find \(\int 2^{x} e^{x} d x,\) we let \(u=2^{x}\) and \(d v=e^{x},\) so \(d u=(\ln 2) 2^{x} d x\) and \(v=e^{x} .\) Using integration by parts, we have $$ \int 2^{x} e^{x} d x=2^{x} e^{x}-\ln 2 \int 2^{x} e^{x} d x $$ Note that \(\int 2^{x} e^{x} d x\) appears twice. Adding \(\ln 2 \int 2^{x} e^{x} d x\) to $$ \begin{aligned} \int 2^{x} e^{x} d x+\ln 2 \int 2^{x} e^{x} d x &=2^{x} e^{x} \\ (1+\ln 2) \int 2^{x} e^{x} d x &=2^{x} e^{x} \\ \int 2^{x} e^{x} d x &=\frac{2^{x} e^{x}}{1+\ln 2}+C \end{aligned} $$ Use this method to evaluate the integrals in Exercises \(59-62\) $$ \begin{aligned} &\int x \ln x d x\\\ &\text { and } d v=d x \text { . Assume }\\\ &x>0 .) \end{aligned} $$

A car accelerates at a constant rate from 0 mph to 60 mph in 30 sec. How far has it traveled after 30 sec?

Use geometry to evaluate each definite integral. \(\int_{2}^{6} 3 d x\)

See all solutions

Recommended explanations on Math Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.