/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q7OQ. Develop a production plan and ca... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring if overtime is necessary to prevent stock-outs at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, \(100 for each temp; layoff, \)200 for each worker laid off; inventory holding, \(5 per unit-quarter; backorder, \)10 per unit; straight time, \(5 per hour; over time, \)8 per hour. Assume that the productivity is 0.5 units per worker hour, with eight hours per day and 60 days per season.

Short Answer

Expert verified

It is reasoned that the complete creation cost of the arrangement is $376,800.

Step by step solution

01

Prepare the production plan of the company as shown below-

Work out the time taken for the development of one unit as displayed underneath:

Usefulness = 0.5 unit each hour

= 2 hours for every unit

The expense of creating every unit is determined during the straight time and during extra time, as displayed underneath:

Straight time work cost = $5 each hour

Usefulness = 2 hours for each unit

In this manner,

Straight time unit cost = Straight Time Labor Cost x Productivity

= $5 x 2 hours/unit

=$10 for each unit

Additional minutes time work cost $8 each hour

Usefulness = 2 hours for each unit

Over the long haul unit cost = Over time work cost x Productivity

= $8 × 2 hours/unit

= $16 for every unit

Now, calculate the number of units produced by each worker as shown below:

Number of units produced per worker per season = 0.5×8×60

02

The production plan is expected to fulfill the need displayed beneath-

The quantity of laborers in the first place is given to be 30.

The equations utilized in the cells are given beneath:

Straight time creation = Number of laborers x 240 units/specialist

Cost of straight time creation = straight time creation x 10

Additional time creation = Demand gauge - straight time creation - starting inventory

Cost of over the long haul creation = over the long haul creation x 16

Rainchecks = Demand gauge - straight time creation - Additional time creation - starting inventory

Laborers recruited = required specialists - available specialists

Laborers terminated = available specialists - required specialists

Recruiting cost = laborers hired×100

Terminating cost laborers terminated x 200

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question: Compare and contrast JIT, MRP, and synchronized manufacturing, stating their main features, such as where each is or might be used, amounts of raw materials and work-in-process inventories, production lead times, and cycle times, and control methods.

Explain the need for the time fences in the master production schedule.

A manufacturing facility has five jobs to be scheduled for production. The following table gives the processing times plus the necessary wait times and other necessary delays for each of the jobs. Assume that today is April 3, that the facility will work every day between now and the due dates, and the jobs are due on the dates shown:

Job

Days of

Actual Processing

Time Required

Days of

Necessary Delay

Time

Total Time

Required

Date Job

Due

1

2

3

4

5

2

5

9

7

4

12

8

15

9

22

14

13

24

16

26

April 30

April 21

April 28

April 29

April 27

Determine two schedules, stating the order in which the jobs are to be done. Use the critical ratio priority rule for one. You may use any other rule for the second schedule as long as you state what it is.

The annual demand for a product is 15,600 units. The weekly demand is 300 units with a standard deviation of 90 units. The cost to place an order is \(31.20, and the time from ordering to receipt is four weeks. The annual inventory carrying cost is \)0.10 per unit. Find the reorder point necessary to provide a 98 percent service probability.

A distributor of large appliances needs to determine the order quantities and reorder points for the various products it carries. The following data refer to a specific refrigerator in its product line: Cost to place an order Holding cost Cost of refrigerator Annual demand Standard deviation of demand during lead time \(100 20 percent of product cost per year \)500 every 500 refrigerators 10 refrigerators 7 days Consider an even daily demand and a 365-day year.

a. What is the economic order quantity?

b. If the distributor wants a 97 percent service probability, what reorder point, R, should be used?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.