/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q9OQ There is an 82 percent chance th... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

There is an 82 percent chance the project below can be completed in X weeks or less. What is X?

Short Answer

Expert verified

The value of X is 18 weeks.

Step by step solution

01

The network diagram


The network diagram for the given table is:

02

The expected time

Expected time = a + 4m + b6

ActivityMost OptimisticMost LikelyMost PessimisticExpected time
A
2511=(B2+4*C2+D2)/6
B333=(B3+4*C3+D3)/6
C135=(B4+4*C4+D4)/6
D6810=(B5+4*C5+D5)/6

Activity

Most Optimistic

Most Likely
Most Pessimistic

Expected time
A25115.5
B3333
C1353
D68108
E47107

Now, we can find the expected path durationas follow:

A - B - D = 5.5 + 3 + 8 = 16.5A - C - E = 5.5 + 3 + 7 = 15.5

The longest time of 16.5 weeks belongs to the path A-B-D and this path would be the critical pathof the project.

03

The value of X

We know that, to find the variance we can use

Variance=b-a62

ActivityMost OptimisticMost LikelyMost PessimisticVariance
A
2511=((D2-B2)/6)^2
B333=((D3-B3)/6)^2
C135=((D4-B4)/6)^2
D6810=((D5-B5)/6)^2
ActivityMost Optimistic

Most Likely
Most PessimisticVariance
A25112.25
B3330
C1350.44444444
D68100.44444444
E47101

Total variance = 2.25 + 0 + 0.44= 2.69

Value of 82% using NORMSINV function in excel:

=NORMSINV(0.82)
0.915365

We know that Expected time = X

Scheduled time = 16.5

Standard deviation = 2.69

Probability distribution = 0.915

Now, probability distribution = Expected time-Scheduled timeStandard deviation0.915 =χ-16.52.69X-16.5=0.915x1.64χ=1.5+16.5χ=18

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and bring in \(25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity completed. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25y30) of this activity complete, it is only 50 percent complete. This part of the project was scheduled to bring in \)150,000 in donations. The final activity is for matching funds. This activity is scheduled to run for the last 10 days of the project and has not started. It is scheduled to bring in an additional \(50,000. So far \)175,000 has been brought in on the project. Calculate the schedule variance, schedule performance index, and cost (actually value in this case) performance index. How is the project going? Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.

Jack Simpson, contract negotiator for Nebula Airframe Company, is currently involved in bidding on a follow-up government contract. In gathering cost data from the first three units, Nebula produced under a research and development contract, he found that the first unit took 2,000 labor hours, the second took 1,800 labor hours, and the third took 1,692 hours.In a contract for three more units, how many labor hours should Simpson plan for?

Question:Order the following major concepts that have helped define the OSCM field on a timeline. Use 1 for the earliest concept to be introduced, and 5 for the most recent.

_________Supply chain management

_________Manufacturing strategy

_________Business analytics

_________Total quality management

_________Electronic commerce

A strategy that meets the needs of shareholders and employees and that preserves the environment.

Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The first unit produced by Lambda took 5,000 hours to produce and required \(250,000 worth of material, equipment usage, and supplies. The second unit took 3,500 hours and used \)200,000 worth of materials, equipment usage, and supplies. Labor is $30 per hour.

a. Lambda was asked to present a bid for 10 additional units as soon as the second unit was completed. Production would start immediately. What would this bid be?

b. Suppose there was a significant delay between the contracts. During this time, personnel and equipment were reassigned to other projects. Explain how this would affect the subsequent bid.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.