/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q8PE Question: A firm is using an ass... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Question: A firm is using an assembly line and needs to produce 500 units during an eight-hour day. What is the required cycle time in seconds?

Short Answer

Expert verified

57.6 secondsis the required cycle time in seconds.

Step by step solution

01

Step-by-Step Solution Step 1: Assembly line

It is a manufacturing method that divides the creation of a product into phases that should be performed in a specific order referred to asan assembly line.

02

Calculation of required cycle time in seconds

The formula is given below:

Cycle time = Net production time (NPT) / Number of units produced

Given,

Number of units produced = 500 units

NPT = 8 hours-day

If we calculate in seconds then,

= 8 x 60 minutes x 60 seconds

Cycle time = (8 x 60 x 60)/500

= 57.6 seconds.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.