/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q.13-1C Question: Prepare X -and R-chart... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Question: Prepare X -and R-charts using these data with the method described in the chapter

Short Answer

Expert verified

Answer

Thebar X and R chartis a type of statistical process monitoring scheme, also known as a control chart.

Step by step solution

01

Determining the X-bar charts

As given,

A2 = 0.73

D3 = 0

D4 = 2.28

N = 4

Calculating the upper and lower limits of X-bar -

Where,

x== 30.40289

A2= 0.73

R-= 5.932155

Upper Control Limit = x=+A2R-

= 30.40289 + (0.73 x 5.932155)

= 30.40289 + 4.33047

= 34.73

Lower Control Limit =x=-A2R-

= 30.40289 - (0.73 x 5.932155)

= 30.40289 - 4.33047

= 26.07

The bar chart is represented below:

02

 Determining the R-chart

Given,

A2 = 0.73

D3 = 0

D4 = 2.28

Calculating the upper and lower limits of R-bar -

Upper Control Limit =D4R-

= 2.28 X 5.932155

= 13.53

Lower Control Limit =D3R-

= 0 X 5.932155

= 0

The R-chart is represented below:

The chart is shown below:

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.