/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q.18-10_1 Question: P18-10 (LO5,6,7) (Long... [FREE SOLUTION] | 91Ó°ÊÓ

91Ó°ÊÓ

Question: P18-10 (LO5,6,7) (Long-Term Contract with Interim Loss) On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of \(8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below.

2017

2018

2019

Contract cost incurred during the year

\)2,880,000

\(2,230,000

\)2,190,000

Estimated cost to complete the contract at 12/31

3,520,000

2,190,000

0

Billings to Fabrik during the year

3,200,000

3,500,000

1,700,000

Instructions

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)

Short Answer

Expert verified

Answer

Gross profit for each year:

2017:$900,000

2018:($130,000)

2019:$330,000

Step by step solution

01

Definition of Income Tax

The fee paid to the government based on the benefits generated during the year from any source is known as income tax. Such tax is progressive in nature.

02

Percentage of completion method

Gross profit Recognized:

Particular

2017

2018

2019

Revenue Recognized

$3,780,000

$2,100,000

$2,520,000

Less: Cost incurred

($2,880,000)

($2,230,000)

($2,190,000)

Gross profit

$900,000

(130,000)

$330,000

Working note:

Calculation of estimated total cost:

2017

2018

2019

Cost incurred during the year

$2,880,000

$5,110,000

$7,300,000

Add: Estimated cost to complete

3,520,000

2,190,000

0

Estimated total cost

$6,400,000

$7,300,000

$7,300,000

The formula for calculating Revenue:

Revenue=costincurredduringyearEstimatedtoptalcost×°ä´Ç²Ô³Ù°ù²¹³¦³Ù±è°ù¾±³¦±ð-revenuerecognizedinpreviouryear

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with 91Ó°ÊÓ!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Franchise Fee, Initial Down Payment) On January 1, 2017, Lesley Benjamin signed an agreement, covering 5 years, to operate as a franchisee of Campbell Inc. for an initial franchise fee of \(50,000. The amount of \)10,000 was paid when the agreement was signed, and the balance is payable in five annual payments of \(8,000 each, beginning January 1, 2018. The agreement provides that the down payment is nonrefundable and that no future services are required of the franchisor once the franchise commences operations on April 1, 2017. Lesley Benjamin’s credit rating indicates that she can borrow money at 11% for a loan of this type.

Instructions

(a) Prepare journal entries for Campbell for 2017-related revenue for this franchise arrangement.

(b) Prepare journal entries for Campbell for 2017-related revenue for this franchise arrangement, assuming that in addition to the franchise rights, Campbell also provides 1 year of operational consulting and training services, beginning on the signing date. These services have a value of \)3,600.

(c) Repeat the requirements for part (a), assuming that Campbell must provide services to Benjamin throughout the franchise period to maintain the franchise value.

Explain the accounting for contract modifications.

Archer Construction Company began work on a \(420,000 construction contract in 2017. During 2017, Archer incurred costs of \)278,000, billed its customer for \(215,000, and collected \)175,000. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Archer’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.

On June 1, 2017, Mills Company sells \(200,000 of shelving units to a local retailer, ShopBarb, which is planning to expand its stores in the area. Under the agreement, ShopBarb asks Mills to retain the shelving units at its factory until the new stores are ready for installation. Title passes to ShopBarb at the time the agreement is signed. The shelving units are delivered to the stores on September 1, 2017, and ShopBarb pays in full. Prepare the journal entries for this bill-and-hold arrangement (assuming that conditions for recognizing the sale as a bill-and-hold sale have been met) for Mills on June 1 and September 1, 2017. The cost of the shelving units to Mills is \)110,000.

On what basis should the transaction price be allocated to various performance obligations? Identify the approaches for allocating the transaction price.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.